Tracking government projects — because promises need receipts 📋
🛣️ LINDEN TO MABURA HILL ROAD: 62% COMPLETE
Project: Linden to Mabura Hill Road Upgrade
Contractor: Alya Construtora (Brazil)
Cost: US$190 million
Status: 62% complete ✅
Minister of Public Works Juan Edghill provided this update following a January 7 meeting with the Brazilian contractors.
What it means: The critical road connecting Linden to the interior is progressing steadily. Once complete, this will significantly improve access to mining areas and interior communities.
What to watch: Weather delays and whether the 2026 completion target holds.
⛽ GAS-TO-ENERGY: MAIN PROJECT ON TRACK, SIDE PROJECTS DELAYED
Main Gas-to-Energy Project (Wales)
- Status: “Steadily progressing” and “firmly on track”
- Target: End of 2026
Gas Bottling Company (GBBL)
- Original Deadline: January 15, 2026
- New Deadline: February 19, 2026 ⚠️
Ammonia & Urea Plant (GAUP)
- Original Deadline: January 22, 2026
- New Deadline: March 5, 2026 ⚠️
Prime Minister Mark Phillips says the deadline extensions are NOT due to lack of interest — companies have submitted requests and meetings are scheduled.
Translation: They got interest but need more time to evaluate. Whether that’s good project management or scope creep, time will tell.
🏟️ BAYROCK STADIUM: OPENING JANUARY 31!
Project: Bayrock Track and Field Stadium (Wismar, Linden)
Location: Region 10 (Upper Demerara-Berbice)
Status: Opening January 31, 2026 ✅
After years of waiting, Linden is FINALLY getting its proper track and field facility!
This is a big win for sports development in Region 10, which has produced numerous national athletes but lacked proper training infrastructure.
Mark your calendars: Official opening is January 31.
✈️ CJIA MODERNIZATION: TALKS WITH IATA
Project: Cheddi Jagan International Airport improvements
Status: In discussion phase
IATA (International Air Transport Association) technical team met with Minister Deodat Indar to discuss:
- Passenger processing efficiency
- Overall airport performance
- Operations modernization
No timeline yet, but the fact that international aviation experts are at the table is progress.
🚢 PORT DEVELOPMENT: BELGIAN INTEREST
Project: Maritime port development/modernization
Status: Exploratory discussions
Port of Antwerp Bruges International (one of Europe’s biggest shipping hubs) sent a delegation to discuss “technical cooperation.”
What this could mean:
- Modern container handling
- Improved logistics
- Better export capacity
Reality check: This is still at the “talking” stage. Nothing signed yet.
📊 PROJECT SCORECARD
| Project | Status | On Track? |
|---|---|---|
| Linden-Mabura Road | 62% complete | ✅ Yes |
| Gas-to-Energy (Main) | Progressing | ✅ Yes |
| Gas Bottling Plant | Deadline extended | ⚠️ Delayed |
| Urea Plant | Deadline extended | ⚠️ Delayed |
| Bayrock Stadium | Opens Jan 31 | ✅ Complete! |
| CJIA Improvements | Discussions | 🔄 Early stage |
| Port Development | Discussions | 🔄 Early stage |
🎯 THE TAKEAWAY
Good news: Major infrastructure projects are moving. The Linden-Mabura road is past the halfway mark, the stadium is about to open, and international partners are interested in ports and airports.
Concerns: The gas-related side projects (bottling and urea) are already seeing deadline slippage. These extensions aren’t dramatic, but they’re worth watching.
The pattern: The government is better at big flagship projects than the supporting infrastructure around them. Let’s see if that changes.
Next week: We check on the housing developments and the New Demerara River Crossing.
Progress Report — Because “coming soon” needs a deadline.